  • Q A contract is to be completed in 50 days and 105 men



    were set to work, each working 8 hours a day. After 25



    days, 2/5th of the work is finished. How many



    additional men be employed so that the work may be



    completed on time, each man now working 9 hours a



    day?



    (1) 34 (2) 36



    (3) 35 (4) 37

    Asked by  6 months ago
     
 
 

Answers (1)

 
  • By , 6 months ago
    Initially 105 men for 25 days for 8 hrs everyday
    So man-hours of work completed  = 105 x 25 x 8 = 21000
    But this is 2/5th of total work
    Let the total work = W
     2/5W = 21000
     W = 52500
    So remaining work = 52500 - 21000 = 31500
    Now let the additional workers be = x
    The entire work has to be completed in 5o days which means that the remaining work has to be done in 25 days
     (105 +x) x 25 x 9  = 31500
         105 + x = 140
            x =  35 men
 
 
 
 